Fluoride Room Project
Project Name
Fluoride Room Project Map.jpg

Fluoride Room Improvements


Project Description
In June 2013, the City Commission discussed the rehabilitation of the fluoride room at the Water Treatment Plant.   

Project Budget and Funding
The cost of the project for improvements are estimated to be between $20,000 and $47,000 funded by Water Revenues.

Construction Year
2014/2015

Current Phase
Preliminary Engineering

Project Engineer
Earles Engineering and Inspections

General Contractor
Not Yet Determined

Tentative Schedule (subject to change)
Design Completion: May 2014
Bid Award:  July 2014
Construction:  October 2014